HIPPS

HIGH INTEGRITY PRESSURE PROTECTION SYSTEMS (HIPPS)

The Engineered Overpressure Safety Barrier — When Relief Is Not Enough

A High Integrity Pressure Protection System is not a valve. It is not a logic solver. It is not a sensor. It is a rigorously engineered, independently certified Safety Instrumented System (SIS) that prevents overpressure of downstream equipment by isolating the high-pressure source faster than a pressure relief valve can respond—and with a higher degree of safety integrity than conventional process shutdown systems can deliver.

HIPPS is specified when the consequence of overpressure is catastrophic, the relieving rate exceeds the practical capacity of relief valves and flare systems, or environmental and economic constraints make conventional relief technically unacceptable. In the hierarchy of overpressure protection, HIPPS sits above relief valves, above operator intervention, and above process alarms. It is the final, independent, auditable barrier.

Hoger SP supplies complete HIPPS packages—valves, actuators, logic solvers, sensors, and all ancillary components—from SIL 3 certified manufacturers with full traceability to IEC 61508 and IEC 61511. We do not assemble components. We deliver certified, tested, and documented safety loops ready for integration, Factory Acceptance Testing, and regulatory submission.


The Fundamental Problem HIPPS Solves

In a conventional process plant, overpressure protection is provided by pressure relief valves (PRVs) discharging to a flare or atmospheric vent system. This works when:

HIPPS

  • The relieving rate is within the flare system’s hydraulic and thermal capacity
  • The relief valve can open fast enough to prevent the pressure from exceeding code limits (typically 110% of MAWP for fire case, 116% for multiple valves)
  • The flare system can handle the combined load of multiple simultaneous relief events
  • Environmental regulations permit flaring of the relieved inventory
  • The relief valve itself functions on demand—a mechanical device that may have been sitting unmoved for years

HIPPS is required when any of these assumptions breaks down:

ScenarioWhy Conventional Relief FailsHIPPS Solution
High-pressure wellhead flowing into lower-rated gathering systemFull wellstream flow at shut-in pressure would overwhelm the gathering system flare capacityHIPPS isolates the well before downstream pressure exceeds design limits
Gas injection compressor discharge into pipelineCompressor discharge pressure exceeds pipeline design pressure. Full compressor throughput relief is impracticalHIPPS closes isolation valves within 2-5 seconds of overpressure detection
Pipeline incoming to processing plantPipeline inventory at high pressure. Flare cannot handle full pipeline blowdownHIPPS isolates the plant inlet. Pipeline inventory remains contained upstream
Brownfield expansionNew production increases relieving load beyond existing flare capacity. Flare system upgrade cost is prohibitiveHIPPS provides overpressure protection without increasing flare load
Subsea tiebackRelief to atmosphere is impossible. Relief to subsea introduces hydrate and environmental risksHIPPS isolates the high-pressure subsea source at or near the wellhead
Environmental constraintsZero-flaring policy, carbon tax, or regulatory prohibition on routine flaringHIPPS prevents the overpressure event entirely rather than managing its consequences

HIPPS Architecture: The Building Blocks

A HIPPS is a complete Safety Instrumented Function (SIF) comprising three elements, all certified as a single loop to the target SIL level.

Element 1: Sensors (Initiators)

Pressure transmitters that continuously monitor the protected system. The HIPPS logic solver receives their signals and initiates a trip when the voting logic threshold is reached.

Typical Voting Architecture:

ArchitectureSensors RequiredTrips WhenSafety AvailabilitySpurious Trip RiskApplication
1oo11Sensor detects overpressureLowLowSIL 1 only. Not recommended for HIPPS
1oo22Either sensor detects overpressureMediumHigher (one sensor fail-high causes trip)SIL 2. Less common
2oo33Any two sensors detect overpressureHighLow (one sensor fail-high does not trip)SIL 3. Industry standard for HIPPS
2oo44Any two sensors detect overpressureVery HighVery LowSIL 3 with enhanced availability. Critical service

Sensor Requirements:

RequirementSpecification
SIL CertificationSIL 3 per IEC 61508. Certified as a subsystem with documented failure data
Response Time< 1 second from pressure change to signal output
Process ConnectionDirect-mounted or remote diaphragm seal. Isolatable for testing and calibration
Communication4-20mA analog + HART digital. Direct-wired to HIPPS logic solver
DiagnosticsContinuous self-diagnostics. Internal fault detection with alarm
RedundancyThree independent sensors. Separate process taps. Separate impulse lines. No common-cause failure points
TestingOnline proof testing capability without removing from service. Comparison checking between transmitters

Element 2: Logic Solver

A dedicated safety PLC or solid-state logic solver that receives sensor signals, executes the voting logic, and commands the final elements to close. It is fundamentally separate from the process control system (DCS/PLC). The DCS controls the process under normal conditions. The HIPPS logic solver protects the process under abnormal conditions. They must not share hardware, software, or power supplies.

Logic Solver

Logic Solver Requirements:

RequirementSpecification
SIL CertificationSIL 3 per IEC 61508. Certified by accredited body (TÜV Rheinland, TÜV Süd, exida, DNV)
ArchitectureFault-tolerant. 1oo2D (one out of two with diagnostics) or 2oo4D redundant architecture. No single point of failure
IndependencePhysically separate from BPCS (Basic Process Control System). Separate power supply. Separate network. Separate marshalling
Response TimeTotal loop response time (sensor detection + logic processing + final element closing) typically <2-5 seconds
DiagnosticsContinuous internal diagnostics covering CPU, memory, I/O modules, communication buses. Fault detection coverage >99%
CommunicationHardwired trip output to final elements. Optional digital communication (ProfiSafe, CIP Safety) for monitored valves
Bypass ManagementControlled, time-limited, password-protected bypass for sensor maintenance. Automatic alarm and logging. Cannot bypass all sensors simultaneously
Event RecordingTime-stamped Sequence of Events (SOE) recording for all trips, alarms, and operator actions. Typically 1ms resolution
Power SupplyRedundant. Dual independent power supplies with automatic switchover. Uninterruptible Power Supply (UPS) backup where required
TestingOnline testing of logic solver without interrupting protection. Automated diagnostic test routines

Major HIPPS Logic Solver Manufacturers We Work With:

  • HIMA Paul Hildebrandt GmbH: HIMax, HIQuad X, HIMatrix systems. The global reference standard for HIPPS logic solvers. TÜV SIL 3 certified
  • Schneider Electric (Triconex): Trident and Tricon CX. Triple modular redundant (TMR) architecture
  • Rockwell Automation (Allen-Bradley): AADvance and Trusted TMR systems
  • Siemens: SIMATIC S7-400F/FH with Failsafe modules. S7-1500F for smaller configurations
  • ABB: AC500-S and Safeguard 400 series
  • Emerson (formerly GE / ICS Triplex): Trusted and AADvance platforms

Note: We do not represent any single logic solver manufacturer. We select and integrate the appropriate platform based on client specification, regional certification requirements, and existing site standardization.


Element 3: Final Elements

The final elements execute the HIPPS command: they close, isolate the high-pressure source, and hold against the full shut-in pressure. The final elements are typically two isolation valves in series (1oo2 architecture) to achieve the required SIL 3 integrity without requiring a single valve to be SIL 3 by itself.

Final Element Architecture:

ArchitectureValves RequiredDescriptionApplication
1oo11Single HIPPS isolation valveSIL 2 only. Not recommended for SIL 3 HIPPS
1oo22 in seriesBoth valves close on trip. Either valve alone stops flow. If one fails to close, the second provides protectionSIL 3. The industry standard for HIPPS final elements
2oo22 in parallelBoth valves must close to stop flow. Higher availability (less spurious trips) but lower safety integrityRare. When spurious trip cost is extreme
2oo33Two out of three valves must closeVery high availability + high safety integrity. For critical subsea or offshore HIPPS

HIPPS Isolation Valve Requirements:

RequirementSpecification
Valve TypeThrough-conduit slab gate valve (API 6D or API 6A) or trunnion-mounted ball valve (API 6D). Full bore. Piggable
Shutoff ClassAPI 598 Zero Leakage or FCI 70-2 Class VI (bubble-tight). Metal-to-metal seal with soft secondary or fully metal-seated with certified low leakage
Fire-SafeAPI 607 or API 6FA certified. Must maintain shutoff during and after fire exposure
SIL CertificationCertified as final element subsystem per IEC 61508. Typically SIL 2 individually. SIL 3 achieved with 1oo2 architecture
Stroking SpeedFull stroke (open to close) typically 2-5 seconds. Faster for high-velocity gas pipelines. Must not cause water hammer
ActuatorPneumatic (spring-return fail-close) or hydraulic (accumulator-return fail-close). Double-acting with stored energy accumulator also used
Stored EnergyFor actuators requiring power to close: dedicated gas accumulator bottle or hydraulic accumulator. Sufficient for full stroke + safety margin
Solenoid ValvesRedundant. 1oo2 or 2oo2 voting. Low solenoid energized to trip (de-energize to trip). Certified SIL 3 as a component
Partial Stroke TestingAutomated PST system. Moves valve 10-20% of stroke at scheduled interval without interrupting process. Verifies valve is not stuck. Extends full proof test interval
Position FeedbackDual redundant position transmitters (4-20mA). Confirms valve fully open or fully closed. Used for diagnostics and PST verification
Sour ServiceNACE MR0175 / ISO 15156 compliant materials. Controlled hardness (≤22 HRC for carbon steel components). HIC/SSC tested
MaterialBody per ASME B16.34. Trim in 316 SS, Duplex, or Inconel 718 depending on service. Hardfaced seat and gate/ball as required

HIPPS Loop Design & SIF Verification

A HIPPS is not a catalogue product. It is an engineered safety loop. The design process is iterative and documented:

HIPPS Loop Design

Step 1: Overpressure Scenario Identification

Define the credible overpressure scenarios. Typically:

  • Upstream well at shut-in tubing pressure (SITP) flowing into lower-rated downstream piping
  • Gas injection compressor at maximum discharge pressure
  • Upstream pipeline at maximum operating pressure (MOP) flowing into lower-rated plant inlet

Step 2: Required Safety Integrity Level (SIL) Determination

Conduct a Safety Integrity Level (SIL) assessment per IEC 61511 using:

  • Layer of Protection Analysis (LOPA): Quantify the gap between the unmitigated risk frequency and the tolerable risk frequency
  • Risk Graph: Qualitative or semi-qualitative method per IEC 61511 Annex D

The LOPA determines the Probability of Failure on Demand (PFDavg) required from the HIPPS. Typically SIL 3 is required (PFDavg < 1×10⁻³ to 1×10⁻⁴).

Step 3: Loop Architecture Selection

Select sensor voting (typically 2oo3), logic solver redundancy (typically 1oo2D), and final element architecture (typically 1oo2) to achieve the target PFDavg.

Step 4: SIF Verification Calculation

Calculate the PFDavg of the complete HIPPS loop:

PFDavg(HIPPS)=PFDavg(Sensors)+PFDavg(LogicSolver)+PFDavg(FinalElements)PFDavg(HIPPS) = PFDavg(Sensors) + PFDavg(Logic Solver) + PFDavg(Final Elements)

Where:

  • Each subsystem PFDavg is calculated from the certified failure rate data (λDU) and the proof test interval (TI)
  • PFDavg(subsystem) ≈ λDU × TI / 2 (for a simple 1oo1 subsystem)
  • PFDavg(2oo3 sensors) is a more complex calculation accounting for common cause failures
  • PFDavg(1oo2 final elements) accounts for common cause failure factor (β-factor, typically 5-10%)

Step 5: Proof Test Interval Determination

The proof test interval must be practical for operations. If the calculated TI is too short (e.g., 6 months on a continuously operating plant), consider:

  • Partial Stroke Testing to extend the full proof test interval
  • Higher-reliability components (lower λDU)
  • More redundant architecture

Step 6: Documentation

The complete HIPPS safety requirements specification, SIF design, verification calculations, and test procedures are compiled into the HIPPS Safety Manual and submitted for regulatory review where required.


HIPPS Testing & Ongoing Validation

HIPPS is not a “fit and forget” system. It requires periodic testing throughout its operational life to maintain the SIL certification.

Test TypeWhat It DoesFrequency
Full Proof TestFull-stroke closure of each HIPPS valve from fully open to fully closed. Verification of sensor trip points. Logic solver function testTypically every 1, 3, or 5 years per SIF verification. During plant turnaround
Partial Stroke Testing (PST)Moves valve 10-20% of stroke without interrupting flow. Verifies valve is not stuck. Detects dangerous undetected failuresTypically monthly or quarterly. Automated. Extends full proof test interval
Sensor ComparisonCompares readings of the three redundant pressure transmitters. Alarms if one deviates from the median by more than a configured toleranceContinuous. Automated in logic solver
Logic Solver DiagnosticsInternal self-test of CPU, memory, I/O, communication. Fault detection coverage >99%Continuous. Automatic fault alarm

HIPPS Documentation Deliverables

Every HIPPS we supply is accompanied by:

DocumentContent
HIPPS Safety Requirements Specification (SRS)Functional description, SIL target, trip setpoints, response time, voting logic
SIL Certificate (Logic Solver)Manufacturer SIL certificate from TÜV/exida/DNV stating SIL 3 capability
SIL Certificate (Final Elements)Valve + actuator + solenoid certificate. SIL 2 or SIL 3 as an assembly
FMEDA ReportsFailure Modes, Effects, and Diagnostic Analysis for each subsystem. Provides λS, λD, λDU, λDD
SIF Verification CalculationDetailed PFDavg calculation for the complete HIPPS loop. Demonstrates compliance with SIL target
HIPPS Safety ManualInstallation, operation, maintenance, proof test, and PST procedures. Bypass management
FAT Procedure & ReportFactory Acceptance Test. Simulated overpressure trip. Verification of response time, voting logic, valve closure
Material Certificates (MTRs)EN 10204 Type 3.1 or 3.2 for all pressure-containing and safety-critical components
Valve Test RecordsShell hydrostatic test. Seat leakage test (API 598 Zero Leakage or FCI 70-2). Functional test with actuator

Global Regulatory Framework

StandardScope
IEC 61508Functional safety of electrical/electronic/programmable electronic safety-related systems. The parent standard
IEC 61511Functional safety for the process industry sector. Application of IEC 61508 to process plants
API RP 14CRecommended practice for analysis, design, installation, and testing of safety systems for offshore production facilities
API RP 521Guide for pressure-relieving and depressuring systems. Addresses HIPPS as an alternative to relief
ASME Section VIII Div 1 / Div 2Pressure vessel code. Recognizes HIPPS as an overpressure protection method in certain jurisdictions
PED (Pressure Equipment Directive)European directive. Acceptance of HIPPS as overpressure protection subject to notified body approval
NORSOK P-100Norwegian standard for process systems. HIPPS accepted
ISO 10418Offshore production installations — analysis, design, installation and testing of basic surface process safety systems

HIPPS vs. Relief Valves: The Total Cost of Ownership

Cost ElementHIPPSRelief Valve + Flare
Capital (Equipment)HIPPS valves, actuators, logic solver, sensors, PST systemRelief valves, flare header, flare tip, knockout drum, flare stack
Capital (Structure)Minimal. Valves in-line with pipingFlare stack structure, guy wires, foundation, heat radiation fencing
Capital (Land)Zero additional landSignificant land for flare radiation exclusion zone
OperatingMinimal. Periodic proof testing. PST automatedFlare purge gas continuous consumption. Flare tip maintenance
EnvironmentalZero emissions during eventFlaring. CO₂, NOx, SOx, unburned hydrocarbons
RegulatoryRequires SIL submission and regulatory approvalEstablished technology. Widely accepted by regulators
Public PerceptionInvisible to publicVisible flame. Noise. Smoke. Community complaints

How We Deliver HIPPS

We are not a HIPPS manufacturer. We are a procurement and integration partner who delivers complete, certified HIPPS packages by:

Deliver HIPPS

  • Manufacturer Selection: We match your project requirements (SIL target, regional certification, client preference, existing site systems) to the appropriate logic solver and final element manufacturers
  • Single-Source Supply: Valves, actuators, logic solver, sensors, solenoids, PST system, and all ancillary components sourced and delivered as one package
  • FAT Coordination: We witness and document Factory Acceptance Testing at the manufacturer’s facility before shipment
  • Documentation Compilation: The complete HIPPS dossier—SIL certificates, FMEDA reports, SIF verification calculation, safety manual, FAT record, material certs—delivered as an auditable package
  • Aftermarket Support: Spare parts, proof testing support, PST system maintenance, actuator seal kits, solenoid replacements

Contact Our Safety Systems Team

HIPPS specification requires detailed process data and safety analysis. Our technical team can support your project from SIL determination through to final documentation. Contact us with your overpressure scenario, and we will work with our manufacturing partners to propose a certified solution.